Client: Worley (EPC to Newcrest Mining)
Worley is a worldwide engineering and construction company of consultants, engineers, construction workers and data scientists. Worley specialises in industries like energy, chemicals and resources sectors.
Project: Cadia Molybdenum Project – Orange NSW, Australia
Newcrest Cadia Molybdenum Project is Australia’s the first Molybdenum processing Plant located near Orange in NSW, Australia. Molybdenum, is a silvery-white metal used in steels and superalloys to enhance strength, prevent corrosion and reduce brittleness, as well as being used in lubricants, fertilisers and pigments.
Duration:
Project Duration for Intellect Automation – July 2019 to Feb 2022 (2 ½ Years)
Fees
Project Fees for Intellect Automation – $ 4.8 Million Australian Dollars
Intellect Scope
Intellect Automation Provided extended engineering and commissioning support from Australia.
Recourses provided are,
- Electrical and Instrumentation Discipline –
- Principal Instrumentation and Control Engineer RPEQ – 1 Nos – (Australia Based)
- Control System engineer (4 Nos) – (Australia Based)
- Electrical Engineer (1 Nos) (Australia Based)
- E&I Site Supervisor (2Nos) (Australia Based)
- E&I Site Technicians (25 Nos) (Australia Based)
- Mechanical Discipline
- Mechanical Site Fitters (4Nos) – (Australia Based)